Idaho's Governor has issued an Executive Order 2006-40 that requires contracts for services performed in the State of Idaho are with businesses that employ individuals who are eligible under Federal and State law to work in the United States. The Division of Public Works is developing procedures to assure that this requirement is met.
| Submission Date |
Project Number |
Project Name |
| 02-11-10 | 08336-1 | Renovate Hailey RC, Roof Overbuild, Division of Military, Hailey, Idaho Addendum 1 |
| 02-11-10 | 10130 | ADA Replace Door Closers, Phase 2, Campus Wide, Eastern Idaho Technical College, Idaho Falls, Idaho |
| 02-18-10 | 08237 | Renovate Graduate School Office Complex, Ph. 2, Center for Teaching & Learning, Idaho State University, Pocatello, Idaho *NOTE NEW BID DATE* *NOTE NEW PRE-BID CONFERENCE DATE* |
| 02-18-10 | 08204 | HVAC System Control Upgrades, Engineering & Tech Bldg., Boise State University, Boise Idaho |
| 02-18-10 | 10603 | Replace Windows, VETB, Division of Veterans Services, Boise, Idaho |
| 02-23-10 | 09227 | ADA Elevator Replacement, Museum of Natural History, Idaho State University, Pocatello, Idaho *NOTE NEW BID DATE* *NOTE NEW PRE-BID CONFERENCE DATE* |
| 03-04-10 | 10152 | Replace HVAC System, Williams Conference Center, Lewis-Clark State College, Lewiston, Idaho. |
No RFQs are available at this time.
No RFQs are available at this time.
Archived Bid Results: 2009, 2008, 2007, 2006, 2005, 2004, and 2003
| Submission Date |
Project Number |
Project Name |
Contractor |
Base Bid |
Alternates |
Awarded |
| 02-04-10 | 10311 | Upgrade HVAC, Panhandle Regional Office, Department of Fish and Game, Coeur d’Alene, Idaho | Tycho Mechanical | $26,813 | 1. $3,275 2. $6,450 |
|
| Pro Heating and Air | $29,780 | 1. $1,910 2. $7,385 |
||||
| Trade Mark Mechanical | $28,100 | 1. $2,900 2. $6,150 |
||||
| 01-28-10 | 10858 & 10859 | Light Construction Service Contracts--Capitol Mall | Hellman Construction | $158,400 | ||
| Alpine Construction | $114,800 | |||||
| ESI | $191,650 | |||||
| Commercial Remodeling | $146,144 | |||||
| Wright Brothers | $150,300 | |||||
| Perkins Construction | $128,300 | |||||
| Kreizenbeck Constructors | $176,400 | |||||
| Northwest Interiors | $153,200 | |||||
| Golis Construction | $116,125 | |||||
| Integrated Interiors | $158,834 | |||||
| 01-21-10 | 08365 | DD/Inpatient Psychiatric Facility, Phase 1, Demolition, ISSH, Department of Health & Welfare, Nampa, Idaho | ASC, Inc | $143,800 | ||
| Tuffy Excavation | $171,191.17 | |||||
| Terra West, Inc | $160,390 | |||||
| AAI Demolition | $184,690 | |||||
| King Excavation | $133,000 | |||||
| Ideal Demolition | $104,700 | |||||
| MJ Excavation | $144,952 | |||||
| Qualitree, Inc. | $98,900 | |||||
| 01-21-10 | 10360 | Demolish Staff House & Bldgs. 6/7, ISSH, Department of Health & Welfare, Nampa, Idaho | ASC, Inc | $183,000 | 1. $12,000 2. $4,500 |
|
| Tuffy Excavation | $255,688.50 | 1. $15,136.50 2. $6,916.50 |
||||
| Terra West, Inc | $318,953 | 1. $20,260 2. $5,083 |
||||
| King Excavation | $173,000 | 1. $20,000 2. $2,000 |
||||
| MJ Excavation | $263,120 | 1. $72,476 2. $3,000 |
||||
| Ideal Demolition | $166,700 | 1. $12,530 2. $4,640 |
||||
| Qualitree, Inc. | $124,800 | 1. $8,500 2. $4,300 |
||||
| 12-29-09 | 10201 | Abate and Demolish, East Junior High School, Boise State University, Boise, Idaho | King Excavation NON-RESPONSIVE |
|||
| Magnum Demolition | $230,500 | 1. $45,500 2. $66,500 |
||||
| Ideal Demolition | $337,700 | 1. $48,800 2. $66,100 |
||||
| Qualitree, Inc. | $384,900 | 1. $44,000 2. $65,600 |
||||
| Grant MacKay NON-RESPONSIVE |
||||||
| Performance Abatement Service | $695,000 | 1. $58,000 2. $84,000 |
||||
| 12-16-09 | 10530 | Security Measures & Parking Expansion, JCC-STA, Department of Juvenile Corrections, St. Anthony, Idaho | Edstrom | $313,400 | 1. $32,000 | |
| Vern Clark | $269,000 | 1. $24,900 | ||||
| TMC | $298,000 | 1. $32,800 | ||||
| BECO | $329,308 | 1. $23,200 | ||||
| HK | $315,000 | 1. $30,000 | ||||
| SE/Z | $276,015 | 1. $21,151 | ||||
| Zollinger | $245,000 | 1. $27,500 | 12-30-09 | |||
| Barry Hayes | $273,631 | 1. $26,781 | ||||
| J & S | $306,300 | 1. $32,000 | ||||
| Shook | $278,665 | 1. $20,411 | ||||
| DL Beck | $329,800 | 1. $24,200 | ||||
| 12-15-09 | 08402 Phase 3 | Replace Heat Pumps, Phase 3, PTF, State Hospital South, Department of Health and Welfare, Blackfoot, Idaho | Hobson Fabricating | $98,900 | 1. $91,800 | |
| TVR | $127,503 | 1. $117,373 | ||||
| Young Electric | $107,300 | 1. $107,300 | ||||
| 12-15-09 | 09010 | HVAC Upgrades, Joe R. Williams (JRW) Bldg., Department of Administration, Boise, Idaho | RM Mechanical | $343,559 | 12-29-09 | |
| 12-11-09 | 10852 & 10853 | Electrical Service Contracts--Capitol Mall | Enterprise | $196,200 | ||
| Tri-State | $168,040 | |||||
| RME | $180,700 | |||||
| NEI | $180,250 | |||||
| Boise Power | $130,550 | |||||
| Quality Electric | $132,700 | |||||
| Primary Electric | $156,500 | |||||
| Power Plus | $184,500 | |||||
| McLean Electric | $124,500 | |||||
| Electric Authority | $158,600 | |||||
| 12-11-09 | 10854 & 10855 | Plumbing Service Contracts--Capitol Mall | Master Rooter | $291,200 | ||
| Cascade Enterprises | $174,800 | |||||
| South Mountain Plumbing | $178,000 | |||||
| RM Mechanical | $206,600 | |||||
| Buss Mechanical | $238,100 | |||||
| DeBest | $187,858 | |||||
| Ridgeway | $319,200 | |||||
| 12-11-09 | 10856 & 10857 | HVAC Service Contracts--Capitol Mall | Carrier | $306,700 | ||
| RM Mechanical | $184,100 | |||||
| PMG | $232,600 | |||||
| ACCO A/C | $304,993 | |||||
| Cascade Enterprises | $193,392 | |||||
| TVR | $266,350 | |||||
| Advanced Heating NON-RESPONSIVE |
||||||
| Hobson Fabricating | $241,300 | |||||
| Ridgeway | $319,200 | |||||
| ClimaTech | $243,500 | |||||
| Trane | $397,700 | |||||
| 12-10-09 | 09090 | Air Conditioning, Physical Education Building, College of Southern Idaho, Twin Falls, Idaho | Reis Plumbing & Heating | $119,975 | ||
| Cascade Enterprises | $184,925 | |||||
| DeBest Plumbing | 156,950 | |||||
| 12-10-09 | 09091 | Air Conditioning, Diesel and Welding Classroom, College of Southern Idaho, Twin Falls, Idaho | TVR | $47,331 | ||
| Sawtooth Sheet Metal | $44,955 | |||||
| Hobson Fabricating | $47,300 | |||||
| TML | $39,400 | |||||
| 11-19-09 | 08114 | Replace HVAC Control System, School for the Deaf and the Blind, Gooding, Idaho | Carrier NON-RESPONSIVE |
|||
| Johnson Controls NON-RESPONSIVE |
||||||
| Yamas Controls | $323,860 | |||||
| Capital City Plumbing | $296,156 | |||||
| ClimaTech | $294,678 | |||||
| ATS Inland NW | $259,500 | 12-09-09 | ||||
| Siemens NON-RESPONSIVE |
||||||
| 11-17-09 | 08076 | Renovate Shower and Restroom, Unit 2; Remodel Kitchen, Install Perimeter Lighting and Replace HVAC Units, Selected Buildings, NICI, Department of Correction, Cottonwood, Idaho | Arnzen Building Construction | $847,655 | 1. $63,561 2. $3,889 |
|
| Bateman Hall | $897,500 | 1. $56,000 2. $6,500 |
||||
| Citadel Construction | $1,022,000 | 1. $48,100 2. $3,800 |
||||
| Ellsworth Kincaid | $774,700 | 1. $57,100 2. $5,054 |
||||
| Golis Construction | $788,838 | 1. $64,742 2. $7,277 |
||||
| Jackson Contractor Group | $834,800 | 1. $35,600 2. $20,800 |
||||
| Kenaston Corporation | $839,000 | 1. $45,792 2. $6,600 |
||||
| KEPHA Construction | $779,000 | 1. $44,420 2. $6,420 |
||||
| S&W Construction | $845,582 | 1. $66,579 2. $5,806 |
||||
| Valley Design & Construction | $1,070,000 | 1. $57,400 2. $15,700 |
||||
| 10-29-09 | 10060 | Re-Roof Units 10, 11, 13, & 14, ISCI, Department of Corrections, Boise Idaho | Conwest | $317,307 | 1. $67,324 | |
| Pro-Tech Roofing | $244,096 | 1. $61,645 | ||||
| Upson Company | $208,270 | 1. $49,825 | ||||
| Alpine Construction | $379,000 | 1. $108,000 | ||||
| JB's Roofing | $265,352 | 1. $40,679 | ||||
| Quality Tile Roofing | $285,062 | 1. $69,892 | ||||
| Hobson Fabricating | $287,000 | 1. $61,600 | ||||
| 10-29-09 | 09540 | Repair/Replace Pedestrian Foot Bridge, Hot Baths, Lava Hot Springs Foundation, Lava Hot Springs, Idaho | Brennan Construction | $44,300 | 11-10-09 | |
| TBP Construction | $73,500 | |||||
| Angle and Associates | $99,000 | |||||
| River's West Construction | $64,100 | |||||
| Vern Clark & Sons Construction | $47,500 | |||||
| 10-15-09 | 10174 | Demolish Mill River House, North Idaho College, Coeur d’Alene, Idaho | S & L Underground *NON-RESPONSIVE* |
|||
| Cannon Hill *NON-RESPONSIVE* |
||||||
| Peck & Peck | $35,457 | 1. $2,685 | ||||
| Apex Construction *NON-RESPONSIVE* |
||||||
| Larsons Demolition *NON-RESPONSIVE* |
||||||
| Blueback Construction | $34,125 | 1. $5,500 | ||||
| Big Sky Development | $30,900 | 1. $2,160 | 10-26-09 | |||
| S. D. Sanders *NON-RESPONSIVE* |
||||||
| Ridgeline Remodel | $46,700 | 1. $700 | ||||
| Talisman *NON-RESPONSIVE* |
||||||
| 10-01-09 | 09233 | Interior Emergency Notification, System, Campus Wide, Idaho State University, Pocatello, Idaho | Barry Hayes Construction | $246,432 | 1. $25,124 | |
| Mountain West Electrical | $126,635 | 1. $25,230 | ||||
| Rivers West Construction | $243,846 | 1. $25,000 | ||||
| System Tech | $257,900 | 1. $15,300 | ||||
| Wheeler Electric | $124,575 | 1. $16,075 | ||||
| Bear River Electric | $248,930 | 1. $24,875 | ||||
| Portneuf Electric | $106,000 | 1. $13,000 | 10-22-09 | |||
| Arco Electric | $202,750 | 1. $22,100 | ||||
| 09-15-09 | 07080 | 1951 Steam Plant Rehabilitation, Old Penitentiary, Idaho State Historical Society, Boise, Idaho | Gafford Construction | $54,961 | 1. $12,045 2. $10,953 3. $18,277 |
|
| Alpine Construction | $59,700 | 1. $11,600 2. $12,400 3. $20,500 |
||||
| KEPHA Construction | $59,277 | 1. $9,445 2. $11,871 3. $20,187 |
||||
| Hellman Construction | $55,664 | 1. $9,493 2. $10,625 3. $15,471 |
10-01-09 | |||
| 09-15-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 21 |
De Best Plumbing | $1,134,700 | 1. $38,768 | |
| RM Mechanical | $1,040,255 | 1. $35,515 | ||||
| Hobson Fabricating | $1,039,000 | 1. $34,326 | 09-24-09 | |||
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 1 NO BIDS RECEIVED |
||||
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 2 |
Quality Concrete Inc. | $238,900 | 1. $650 2. $0 |
|
| E-M Construction Company | $183,895 | 1. $605 2. $0 |
09-22-09 | |||
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 3 |
Pristine Pools | $1,246,950 | 09-25-09 | |
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 4 |
Frazier Masonry | $336,425 | 1. $16,700 | |
| TMC | $237,320 | 1. $10,159 | 10-01-09 | |||
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 5 |
B and B Steel | $728,350 | 1. $23,915 | |
| Boise Steel | $790,000 | 1. $21,533 | ||||
| Steel West | $669,999 | 1. $24,500 | 09-25-09 | |||
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 6 |
ISI | $305,175 | 1. $40,100 | |
| NW Interiors | $573,520 | 1. $29,967 | ||||
| Lombac Construction | $306,200 | $28,000 | 09-29-09 | |||
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 7 |
Idaho Custom Wood Products | $23,000 | 1. $0 2. $0 |
09-29-09 |
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 8 |
SealCo., Inc. | $27,800 | 1. $85 2. $0 |
09-24-09 |
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 9 |
G & G Insulation | $10,885 | 1. $158 | 09-24-09 |
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 10 |
Skyline Sheet Metal | $213,594 | 1. $0 2. $0 |
|
| Hobson Fabricating Corporation | $155,700 | 1. $3,800 2. $0 |
09-24-09 | |||
| Kilgore | $213,825 | 1. $-2,250 | ||||
| Upson Company | $211,700 | 1. $15,800 | ||||
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 11 |
Pro-Tech Roofing | $222,467 | 1. $20,278 | |
| Hobson Fabricating Corporation | $168,200 | 1. $3,500 | 09-24-09 | |||
| Upson Company | $198,000 | 1. $0 | ||||
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 12 |
Masonry Center | $52,756 | 1. $6,717 | 09-24-09 |
| Architectural Building Supply | $58,350 | 1. $6,000 | ||||
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 13 |
Custom Glass | $469,640 | 1. $7,350 | 09-24-09 |
| D & A Glass | $478,066 | 1. $16,724 | ||||
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 14 |
Wall 2 Wall | $5,070 | 1. $30,310 | |
| Great Floors | $6,647 | 1. $22,000 | 09-24-09 | |||
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 15 NO BIDS RECEIVED |
||||
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 16 |
Creechley Tile NON-RESPONSIVE |
|||
| Mesa Tile | $58,604 | 1. $0 2. $528 |
12-10-09 | |||
| Stone Canyon | $56,141.83 | 1. N/A 2. N/A |
||||
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 17 |
SBI | $148,495 | 1. $0 2. $0 |
09-29-09 |
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 18 |
Eccles Painting | $53,850 | 1. $1,600 2. $0 |
|
| National Coatings | $56,500 | 1. $1,925 | ||||
| Color Craft | $29,990 | 1 $1,550 | 09-25-09 | |||
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 19 |
Commercial Window Coverings | $23,777 | 09-23-09 | |
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 20 |
SimplexGrinnell | $41,159 | 1. $3,741 | |
| Phoenix | $34,399 | 1. $2,177 | ||||
| Shilo | $31,430 | 1. $2,570 | 09-25-09 | |||
| TVFP | $37,500 | 1. $1,500 | ||||
| Absolute | $35,703 | 1. $2,500 | ||||
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 22 |
Doherty | $296,700 | 1. $9,050 | |
| RME | $289,900 | 1. $6,500 | 09-22-09 | |||
| Power Plus | $294,532 | 1. $10,855 | ||||
| Commercial Electric | $347,000 | 1. $8,807 | ||||
| Idaho Electric | $343,440 | 1. $12,440 | ||||
| Tri State | $327,387 | 1. $10,400 | ||||
| Anderson Wood | $329,740 | 1. $10,750 | ||||
| Lea Electric | $388,665 | 1. $13,344 | ||||
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 23 |
Robert P Jones NON-RESPONSIVE |
|||
| Power Plus | $179,965 | 09-25-09 | ||||
| G & S Excavation | $245,512 | |||||
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 24 |
Idaho Sand & Gravel | $8,860 | 09-25-09 | |
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 25 |
Lawn Co | $32,800 | ||
| Avalon Landscapes | $63,995 | |||||
| New West Landscapes | $24,509.35 | 09-24-09 | ||||
| 09-10-09 | 08669 | Aquatic Center Addition, Boise State University, Boise Idaho Bid Package 26 |
Power Plus | $27,010 | 09-25-09 | |
| 09-10-09 | 09331 | Improvements, Lewiston RC, Division of Military, Lewiston, Idaho | S & W Construction | $309,402 | 1. $36,800 2. $9,781 3. $9,292 |
|
| Kenaston Corporation | $308,000 | 1. $31,300 2. $11,650 3. $9,280 |
||||
| Golis Construction | $352,500 | 1. $39,800 2. $10,200 3. $9,600 |
||||
| ML Albright & Sons | $305,600 | 1. $28,400 2. $18,500 3. $5,620 |
09-15-09 | |||
| 09-10-09 | 09606 | Administration Building, Boise, Division of Veterans Services, Boise Idaho | Wright Brothers | $844,283 | 1. $30,094 2. $6,718 3. $3,592 4. $6,649 5. $2,488 |
|
| Luekenga Construction | $926,021 | 1. $34,675 2. $10,028 3. $6,649 4. $6,715 5. $3,917 |
||||
| The Ewing Company | $924,500 | 1. $31,422 2. $6,886 3. $3,780 4. $6,920 5. $3,108 |
||||
| Alpine Construction | $874,800 | 1. $32,400 2. $7,600 3. $3,900 4. $7,000 5. $3,200 |
||||
| Commercial Remodeling | $857,995 | 1. $27,560 2. $5,412 3. $1,163 4. $6,853 5. $2,564 |
||||
| Kreizenbeck Constructors | $933,200 | 1. $31,480 2. $6,864 3. $3,308 4. $7,547 5. $3,099 |
||||
| Dave Allen Construction | $848,000 | 1. $32,561 2. $7,819 3. $1,309 4. $7,249 5. $3,256 |
||||
| Gafford Construction | $876,355 | 1. $34,102 2. $10,034 3. $3,797 4. $7,689 5. $3,157 |
||||
| CSDI Construction | $827,000 | 1. $30,900 2. $6,600 3. $3,800 4. $6,700 5. $3,000 |
09-30-09 | |||
| Guho Corporation | $920,000 | 1. $33,000 2. $2,700 3. $4,400 4. $7,900 5. $3,900 |
||||
| Ovard Construction | $866,700 | 1. $33,270 2. $7,470 3. $4,000 4. $8,000 5. $3,300 |
||||
| Stock CMS | $845,000 | 1. $34,870 2. $11,183 3. $1,272 4. $7,643 5. $2,696 |
||||
| CM Company | $958,894 | 1. $34,093 2. $7,402 3. $3,594 4. $8,200 5. $2,410 |
||||
| Excelsior Construction | $900,000 | 1. $30,900 2. $7,000 3. $3,600 4. $7,300 5. $2,500 |
||||
| KEPHA Construction | $882,714 | 1. $30,739 2. $6,838 3. $1,222 4. $6,769 5. $3,040 |
||||
| SE/Z Construction | $888,444 | 1. $32,622 2. $7,031 3. $1,253 4. $7,066 5. $2,144 |
||||
| Scott Hedrick Construction | $897,700 | 1. $34,200 2. $6,880 3. $3,700 4. $6,800 5. $2,500 |
||||
| Radix Construction | $979,454 | 1. $32,295 2. $6,250 3. $4,406 4. $6,590 5. $2,960 |
||||
| AEI | $969,450 | 1. $27,600 2. $8,500 3. $4,580 4. $7,360 5. $2,930 |
||||
| Ellsworth Kincaid Construction | $871,084 | 1. $31,780 2. $6,900 3. $3,200 4. $6,920 5. $2,625 |
||||
| Steed Construction | $892,600 | 1. $31,350 2. $8,500 3. $7,100 4. $7,250 5. $3,450 |
||||
| Perkins Construction | $889,000 | 1. $37,800 2. $7,700 3. $3,800 4. $7,400 5. $3,300 |
||||
| 09-10-09 | 10310 | Re-Roof Southwest Regional Office, Nampa, Department of Fish and Game, Nampa, Idaho | Quality Tile Roofing | $72,869 | Unit Price: $1,165 1. $1,275 2. $4,975 |
|
| Pro-Tech Roofing | $63,156 | Unit Price: $2,500 1. $460 2. $6,973 |
||||
| Upson Company | $65,981 | Unit Price: $1,025 1. $369 2. $6,287 |
||||
| Z Steel | $61,223 | Unit Price: $1,260 1. $1,800 2. $5,677 |
||||
| 09-09-09 | 09193 | General Building Infrastructure, Multi-Purpose Classroom Building, Boise State University, Boise, Idaho | Ovard Construction | $783,999 | 1. $112,899 2. $59,433 3. $83,199 |
|
| Stock Construction Management | $724,000 | 1. $111,464 2. $43,578 3. $78,334 |
09-23-09 | |||
| Alpine Construction | $760,000 | 1. $95,000 2. $43,000 3. $75,000 |
||||
| Excelsior Construction | $748,000 | 1. $108,700 2. $43,500 3. $72,998 |
||||
| Steed Construction | $752,800 | 1. $107,800 2. $55,300 3. $78,600 |
||||
| McAlvain Construction, Inc. | $836,951 | 1. $98,866 2. $58,821 3. $76,550 |
||||
| Scott Hedrick Construction | $752,500 | 1. $96,000 2. $43,600 3. $73,000 |
||||
| Ellsworth Kincaid Construction | $809,741 | 1. $112,300 2. $57,900 3. $83,500 |
||||
| Engineered Structures, Inc. | $809,700 | 1. $100,216 2. $44,057 3. $74,325 |